Bay Lake, FL Permit Fees (2026)

Building permit fees and building, electrical, plumbing, mechanical/HVAC, and roofing permit fees for Bay Lake, straight from the official fee schedule, with a free permit fee calculator below.

In Bay Lake, a building permit for a $50,000 remodel runs $473.90 in permit fees, a $20,000 re-roof $251.22, a $10,000 HVAC change-out $175.00, a $10,000 electrical panel upgrade or rewire $175.00, and a $10,000 whole-house repipe $175.00. Totals include the documented surcharges and minimum fees. Each figure is that single permit only: a job that combines trades, like a kitchen remodel with electrical and plumbing work, pays each applicable permit. Pick a project to load it in the calculator below.

Jump to Permit Fee Calculator
Source

CFTOD Board of Supervisors Meeting Package, Nov. 15, 2023 – Agenda Item 9.1, Resolution No. 656 (Building & Safety Department Fee Schedule, exhibit pp. 1-6 = PDF pp. 1307-1312)

Covers building, electrical, plumbing, mechanical/HVAC, and roofing permits. Minimum permit fee: $60.00.

Apply online at the Bay Lake permit portal, or call (407) 828-2034.

How Bay Lake values a job: Chargeable valuation is the full contract value of the work. For building, sign, roof, pool and amusement device permits this is the contract value of the installation or alteration including all new materials, equipment, and owner furnished items. For electrical, plumbing and mechanical trade permits it is the signed contract amount, meaning labor and installation costs including the value of all new equipment and material. The district requires a valuation verification form with the application.

Schedule effective November 1, 2023. Last verified: September 27, 2026

This schedule predates Florida's HB 803 (July 2026). Jurisdictions statewide are adopting updated schedules; we check sources weekly. What HB 803 changed

Bay Lake Permit Fee Schedule

Every documented rule for each permit type, straight from the official schedule.

Building Permit Fees in Bay Lake

All projects
tiered rates by job value, minimum $60.00
Up to $1,000
$60.00
Over $1,000, up to $25,000
$60.00 plus $5.50 per additional $1,000
Over $25,000, up to $50,000
$192.00 plus $4.75 per additional $1,000
Over $50,000, up to $100,000
$310.75 plus $4.25 per additional $1,000
Over $100,000, up to $2,000,000
$523.25 plus $3.75 per additional $1,000
Over $2,000,000
$7,648.25 plus $3.00 per additional $1,000
Plan Review Fee
50% of the permit fee
State Building Code Administrators Surcharge (F.S. 468.631)
1.5% of the permit fee, minimum $2.00
State Building Permit Surcharge (F.S. 553.721)
1% of the permit fee, minimum $2.00
Sponsor This Page
Be the Featured General Contractor in Bay Lake

Homeowners and contractors planning a project check Bay Lake building permit fees here first. One sponsor per trade, flat monthly rate.

Advertise on This Page

Bay Lake Permit Fee Calculator

Pick a permit type and adjust the job value. Total updates instantly, itemized below.

Permit type
Project type

Fees in Bay Lake are the same either way.

Kind of work

Fees in Bay Lake are the same either way.

$
$2,500$500,000
Estimated building permit fee
$473.90
Included in this total
Building Permit Fee$310.75
$192.00 + 25 × $4.75 per $1,000 over $25,000, minimum $60.00 (see the fee table above)
Plan Review Fee$155.38
State Building Code Administrators Surcharge (F.S. 468.631)$4.66
State Building Permit Surcharge (F.S. 553.721)$3.11
Total Estimate$473.90

Chargeable valuation is the full contract value of the work. For building, sign, roof, pool and amusement device permits this is the contract value of the installation or alteration including all new materials, equipment, and owner furnished items. For electrical, plumbing and mechanical trade permits it is the signed contract amount, meaning labor and installation costs including the value of all new equipment and material. The district requires a valuation verification form with the application.

Estimate only. Confirm with the Bay Lake building department before applying. Apply online. Phone: (407) 828-2034. Permit fees only; excludes impact fees, utility connection charges, and other non-permit charges.

Sponsor This Page
Be the Featured General Contractor in Bay Lake

Homeowners and contractors planning a project check Bay Lake building permit fees here first. One sponsor per trade, flat monthly rate.

Advertise on This Page

How to Apply for a Permit in Bay Lake

Building permits inside Bay Lake are issued by the Central Florida Tourism Oversight District, the successor to the Reedy Creek Improvement District, which serves as the building official for both Bay Lake and Lake Buena Vista under one fee schedule. All permit applications are submitted electronically through the district's Accela Citizen Access portal at permitting.oversightdistrict.org; there is no in person or mail in path. Before applying, your contractor must be registered with the district's Building and Safety Department: registration documents are emailed to Permitting@oversightdistrict.org and include the state contractor certification, a Florida county business tax receipt, proof of workers compensation insurance of $1,000,000 naming the district, a notarized contractor registration form, and a notarized power of attorney or agent form naming everyone authorized to apply for and receive permits. Through the portal you complete the application, upload plans as PDFs, pay fees, track review, schedule inspections, and request certificates of occupancy. Drawings must be digitally signed and sealed when the valuation is $25,000 or more, and the owner signs when the value exceeds $2,500. A recorded Notice of Commencement is required over $5,000, or over $15,000 for heating and air conditioning replacement, uploaded before the first inspection. Fees are due when the application passes sufficiency review; the district accepts credit cards, cash, checks, and money orders, and all fees are non refundable. Inspections are scheduled through the portal or the automated line at (407) 828-4466; normal inspection hours are 6:00 a.m. to 6:00 p.m., Monday through Friday.

Source: Bay Lake application instructions

Apply online: Bay Lake permit portal
Building Department Contact
Address
Central Florida Tourism Oversight District, Building and Safety Department, 1900 Hotel Plaza Blvd., Lake Buena Vista, FL 32830
Mailing Address
P.O. Box 10170, Lake Buena Vista, FL 32830-0170
Inspection Scheduling (IVR)
(407) 828-4466
Hours
Inspections 6:00 a.m. to 6:00 p.m., Monday through Friday; no published counter hours, all intake is online

Bay Lake Permit Fee FAQs

How Much Does a Building Permit Cost in Bay Lake?

The building permit for a $50,000 residential remodel runs $473.90, including the documented surcharges and minimum fees. The estimate is built from Bay Lake's sourced fee schedule, and it covers the building permit alone; a job that combines trades pays each applicable permit. Calculate your job's value for an itemized total.

How Much Does a Roofing Permit Cost in Bay Lake?

The roofing permit for a $20,000 residential re-roof runs $251.22, based on Bay Lake's sourced fee schedule.

How Are Permit Fees Calculated in Bay Lake?

A residential building permit is tiered rates by job value, minimum $60.00. Electrical, Plumbing, Mechanical / HVAC, and Roofing permits scale with the value of the job. Every rate comes straight from the sourced fee schedule above. Enter your job's details for an itemized total.

What Is the Minimum Permit Fee in Bay Lake?

The sourced schedule sets a minimum permit fee of $60.00; small jobs pay at least that much before surcharges. The calculator applies it automatically.

What Surcharges Are Added to Permits in Bay Lake?

On top of the base permit fee, the sourced schedule adds Plan Review Fee (50% of the permit fee), State Building Code Administrators Surcharge (F.S. 468.631) (1.5% of the permit fee, minimum $2.00) and State Building Permit Surcharge (F.S. 553.721) (1% of the permit fee, minimum $2.00). These are included in every estimate on this page.

Do I Need a Permit for a Small Residential Job in Bay Lake?

Florida's HB 803 (effective July 2026) exempts certain single-family work under $7,500 from permitting statewide, excluding electrical, plumbing, structural, mechanical, and gas work. Confirm with the building department whether your job qualifies before skipping a permit. Read what HB 803 changed and what it saves.

Where Do These Fees Come From?

Every figure on this page is sourced from CFTOD Board of Supervisors Meeting Package, Nov. 15, 2023 – Agenda Item 9.1, Resolution No. 656 (Building & Safety Department Fee Schedule, exhibit pp. 1-6 = PDF pp. 1307-1312). See the official schedule. Last verified .

Other Jurisdictions in Orange County

Jobs inside another city's limits are permitted by that city; unincorporated areas by the county.

New to Florida permit fees? Read our Florida permit fee guide: how schedules are set, the statutory surcharges, and what HB 803 changed in 2026. Pulling a commercial permit or a small residential job? See what HB 803 lets you save. Wondering whether fees changed this year? See which Florida fee schedules are new.

Contact

Get in Touch

Missing a jurisdiction? Spotted a fee that looks off? Request coverage for a city or county, report an issue, or ask about sponsorship. We typically reply within one business day.