New Port Richey, FL Permit Fees (2026)

Building permit fees and building, electrical, plumbing, mechanical/HVAC, and roofing permit fees for New Port Richey, straight from the official fee schedule, with a free permit fee calculator below.

New Port Richey's FY 2026-2027 fee schedule, approved September 15, 2026, covers the fiscal year beginning October 1, 2026. The building and trade permit fees shown here are unchanged from the FY 2025-2026 schedule. See the official notice

In New Port Richey, a building permit for a $50,000 remodel runs $565.00 in permit fees, a $20,000 re-roof $206.00, a $10,000 HVAC change-out $154.50, a $10,000 electrical panel upgrade or rewire $154.50, and a $10,000 whole-house repipe $154.50. Totals include the documented surcharges and minimum fees. Each figure is that single permit only: a job that combines trades, like a kitchen remodel with electrical and plumbing work, pays each applicable permit. Pick a project to load it in the calculator below.

Jump to Permit Fee Calculator
Source

City of New Port Richey FY 2026-2027 Comprehensive Fee Schedule (approved by Resolution No. 2026-26, September 15, 2026)

Covers building, electrical, plumbing, mechanical/HVAC, and roofing permits.

How New Port Richey values a job: New Port Richey calculates permit fees on the contract price; the Building Official may instead set the value from ICC valuation data or other nationally recognized sources.

Schedule effective October 1, 2026. Last verified: September 27, 2026

This schedule took effect after Florida's HB 803 (July 2026). We check sources weekly. What HB 803 changed

New Port Richey Permit Fee Schedule

Every documented rule for each permit type, straight from the official schedule.

Roofing Permit Fees in New Port Richey

Residential (1–2 family): Re-roof (residential)
1% of job value, minimum $150.00
Commercial / 3+ units: Re-roof (commercial)
1% of job value, minimum $250.00
State Building Permit Surcharges (F.S. 553.721 + 468.631, combined)
3% of the permit fee, minimum $4.00
After-Hours Permit Processing or Inspection (if applicable)
$200.00
Alternative Materials and Methods Request (if applicable)
$350.00
Change of Contractor (if applicable)
$75.00
Change or Add Subcontractor (if applicable)
$75.00
Duplicate Permit Card (if applicable)
$5.00
Expired Permit Reinstatement (if applicable)
$250.00
Permit Extension (first 90 days) (if applicable)
$100.00
Permit Extension (second 90 days) (if applicable)
$200.00
Permit Revision (Commercial) (if applicable)
$250.00
Permit Revision (Residential) (if applicable)
$150.00
Re-inspection Fee (1st) (if applicable)
$75.00
Re-inspection Fee (2nd) (if applicable)
$150.00
Re-inspection Fee (3rd) (if applicable)
$200.00
Resubmittal Fee (after two submittals) (if applicable)
$200.00
Written Code Interpretation (if applicable)
$350.00
Sponsor This Page
Be the Featured Roofer in New Port Richey

Homeowners and contractors planning a project check New Port Richey roofing permit fees here first. One sponsor per trade, flat monthly rate.

Advertise on This Page

New Port Richey Permit Fee Calculator

Pick a permit type and adjust the job value. Total updates instantly, itemized below.

Permit type
Project type
Kind of work
$
$500$100,000
Estimated roofing permit fee
$206.00
Included in this total
Roofing Permit Fee$200.00
$20,000 × 1%, minimum $150.00
State Building Permit Surcharges (F.S. 553.721 + 468.631, Combined)$6.00
Total Estimate$206.00

New Port Richey's FY 2026-2027 fee schedule, approved September 15, 2026, covers the fiscal year beginning October 1, 2026. The building and trade permit fees shown here are unchanged from the FY 2025-2026 schedule. See the official notice

New Port Richey calculates permit fees on the contract price; the Building Official may instead set the value from ICC valuation data or other nationally recognized sources.

Estimate only. Confirm with the New Port Richey building department before applying. Permit fees only; excludes impact fees, utility connection charges, and other non-permit charges.

Sponsor This Page
Be the Featured Roofer in New Port Richey

Homeowners and contractors planning a project check New Port Richey roofing permit fees here first. One sponsor per trade, flat monthly rate.

Advertise on This Page

New Port Richey Permit Fee FAQs

How Much Does a Building Permit Cost in New Port Richey?

The building permit for a $50,000 residential remodel runs $565.00, including the documented surcharges and minimum fees. The estimate is built from New Port Richey's sourced fee schedule, and it covers the building permit alone; a job that combines trades pays each applicable permit. Calculate your job's value for an itemized total.

How Much Does a Roofing Permit Cost in New Port Richey?

The roofing permit for a $20,000 residential re-roof runs $206.00, based on New Port Richey's sourced fee schedule.

How Are Permit Fees Calculated in New Port Richey?

A residential building permit is 1% of job value, minimum $200.00. Electrical, Plumbing, and Roofing permits scale with the value of the job; Mechanical / HVAC permits are flat fees. Every rate comes straight from the sourced fee schedule above. Enter your job's details for an itemized total.

What Surcharges Are Added to Permits in New Port Richey?

On top of the base permit fee, the sourced schedule adds State Building Permit Surcharges (F.S. 553.721 + 468.631, combined) (3% of the permit fee, minimum $4.00). These are included in every estimate on this page.

Do I Need a Permit for a Small Residential Job in New Port Richey?

Florida's HB 803 (effective July 2026) exempts certain single-family work under $7,500 from permitting statewide, excluding electrical, plumbing, structural, mechanical, and gas work. Confirm with the building department whether your job qualifies before skipping a permit. Read what HB 803 changed and what it saves.

Where Do These Fees Come From?

Every figure on this page is sourced from City of New Port Richey FY 2026-2027 Comprehensive Fee Schedule (approved by Resolution No. 2026-26, September 15, 2026). See the official schedule. Last verified .

Other Jurisdictions in Pasco County

Jobs inside another city's limits are permitted by that city; unincorporated areas by the county.

New to Florida permit fees? Read our Florida permit fee guide: how schedules are set, the statutory surcharges, and what HB 803 changed in 2026. Pulling a commercial permit or a small residential job? See what HB 803 lets you save.

Contact

Get in Touch

Missing a jurisdiction? Spotted a fee that looks off? Request coverage for a city or county, report an issue, or ask about sponsorship. We typically reply within one business day.