FreeEvery fee straight from the official city and county fee schedules. No signup.

Building Permit Fees in Neptune Beach, FL (2026)

In Neptune Beach, a building permit for a $50,000 remodel runs $599.63 in permit fees, a $20,000 re-roof $228.58, a $10,000 HVAC change-out $91.00, a $10,000 electrical panel upgrade or rewire $351.58, and a $10,000 whole-house repipe $233.70. Totals include the documented surcharges and minimum fees; where the schedule prices by unit, figures assume a 3-ton system and a 15-fixture scope. Each figure is that single permit only: a job that combines trades, like a kitchen remodel with electrical and plumbing work, pays each applicable permit. Pick a project to load it in the calculator below.

Source

Resolution No. 2026-10, Exhibit A (2026 Fee Resolution), City of Neptune Beach

Covers building, electrical, plumbing, mechanical/HVAC, and roofing permits.

Schedule effective July 20, 2026. Last verified: August 19, 2026

Schedule adopted under Florida's HB 803 permit fee rules (effective July 2026). What HB 803 changed

Neptune Beach Permit Fee Schedule

Every documented rule for each permit type, straight from the official schedule.

Building Permit Fees in Neptune Beach

All projects
tiered rates (see fee table) (Tier boundaries below $10,500 closed from printed non-contiguous ranges (fee amounts unchanged from print); $100,001-$105,000 sub-band computed as $105 + 90x$7 = $735 per the marginal formula's own stated $100,000 increment cap.)
$0–$100
$61.00
$100–$1,000
$80.00
$1,000–$2,000
$92.00
$2,000–$3,000
$109.00
$3,000–$4,000
$116.00
$4,000–$5,000
$122.00
$5,000–$6,000
$128.00
$6,000–$7,000
$135.00
$7,000–$8,000
$141.00
$8,000–$9,000
$146.00
$9,000–$10,500
$153.00
$10,500–$100,000
$153.00 + $7.00 per $1,000
$100,000–$105,000
$783.00
$105,000–$525,000
$725.00 + $4.00 per $1,000
Over $525,000
$1,931.00 + $1.50 per $1,000
Arborist Review Fee
$4.80 (10% x $48 issuance fee = $4.80.)
Building Official Review Fee
$24.00 (50% x $48 issuance fee (source's stated basis) = $24.00, not 50% of the total computed building permit fee.)
Building Permit Plan Submittal Completeness Check Fee
$79.00
Engineer/Public Works Review Fee
$4.80 (10% x $48 issuance fee = $4.80.)
FL Building Code Enforcement Surcharge (F.S. 468.631)
1.5% of the permit fee, minimum $2.00
FL Building Code Training Surcharge (F.S. 553.721)
1% of the permit fee, minimum $2.00
Floodplain Review Fee
$14.40 (30% x $48 issuance fee = $14.40.)
Neptune Beach - Fire Life Safety Review
20% of the permit fee
Neptune Beach - Fire Plan Review
45% of the permit fee
Planning Review Fee
$19.20 (40% x $48 issuance fee = $19.20.)
Stormwater/Erosion/MS-4 Review Fee
$9.60 (20% x $48 issuance fee = $9.60.)

† Corroborated across official sources, but not printed line-for-line in the linked schedule.

‡ Awaiting confirmation from the jurisdiction.

Sponsor This Page
Be the Featured General Contractor in Neptune Beach

Homeowners and contractors planning a project check Neptune Beach building permit fees here first. One sponsor per trade, flat monthly rate.

Advertise on This Page

Neptune Beach Permit Fee Calculator

Pick a permit type and adjust the job value. Total updates instantly, itemized below.

Permit type
Project type
Kind of work

Fees in Neptune Beach are the same either way.

$
$2,500$500,000
Estimated building permit fee
$599.63
Building permit fee$433.00
tiered rates (see fee table) (Tier boundaries below $10,500 closed from printed non-contiguous ranges (fee amounts unchanged from print); $100,001-$105,000 sub-band computed as $105 + 90x$7 = $735 per the marginal formula's own stated $100,000 increment cap.)
Arborist Review Fee$4.80
Building Official Review Fee$24.00
Building Permit Plan Submittal Completeness Check Fee$79.00
Engineer/Public Works Review Fee$4.80
FL Building Code Enforcement Surcharge (F.S. 468.631)$6.50
FL Building Code Training Surcharge (F.S. 553.721)$4.33
Floodplain Review Fee$14.40
Planning Review Fee$19.20
Stormwater/Erosion/MS-4 Review Fee$9.60
Total Estimate$599.63

Fees are charged on the value your jurisdiction assigns to the work; many use ICC square-footage valuation tables or your contract price, whichever is greater. If the assigned value is higher than your contract, the actual fee will be higher too.

Estimate only. Confirm with the Neptune Beach building department before applying.

Sponsor This Page
Be the Featured General Contractor in Neptune Beach

Homeowners and contractors planning a project check Neptune Beach building permit fees here first. One sponsor per trade, flat monthly rate.

Advertise on This Page

Neptune Beach Permit Fee FAQs

How Much Is a Building Permit in Neptune Beach?

The building permit for a $50,000 residential remodel runs $599.63, including the documented surcharges and minimum fees. The estimate is built from Neptune Beach's sourced fee schedule, and it covers the building permit alone; a job that combines trades pays each applicable permit. Calculate your job's value for an itemized total.

How Much Is a Roofing Permit in Neptune Beach?

The roofing permit for a $20,000 residential re-roof runs $228.58, based on Neptune Beach's sourced fee schedule.

How Are Permit Fees Calculated in Neptune Beach?

A residential building permit is tiered rates (see fee table) (Tier boundaries below $10,500 closed from printed non-contiguous ranges (fee amounts unchanged from print); $100,001-$105,000 sub-band computed as $105 + 90x$7 = $735 per the marginal formula's own stated $100,000 increment cap.). Electrical and Roofing permits scale with the value of the job; Plumbing permits are priced per fixture; Mechanical / HVAC permits are priced per ton. Every rate comes straight from the sourced fee schedule above. Enter your job's details for an itemized total.

What Surcharges Are Added to Permits in Neptune Beach?

On top of the base permit fee, the sourced schedule adds FL Building Code Enforcement Surcharge (F.S. 468.631) (1.5% of the permit fee, minimum $2.00), FL Building Code Training Surcharge (F.S. 553.721) (1% of the permit fee, minimum $2.00), Neptune Beach - Fire Life Safety Review (20% of the permit fee) and Neptune Beach - Fire Plan Review (45% of the permit fee). These are included in every estimate on this page.

Do I Need a Permit for a Small Residential Job in Neptune Beach?

Florida's HB 803 (effective July 2026) exempts certain single-family work under $7,500 from permitting statewide, excluding electrical, plumbing, structural, mechanical, and gas work. Confirm with the building department whether your job qualifies before skipping a permit. Read what HB 803 changed.

Where Do These Fees Come From?

Every figure on this page is sourced from Resolution No. 2026-10, Exhibit A (2026 Fee Resolution), City of Neptune Beach. See the official schedule. Last verified .

Compare Permit Fees Across Duval County

The same job, priced by each jurisdiction's own fee schedule. Across Duval County's 5 covered jurisdictions, a building permit for a $50,000 remodel runs from $400.25 (Unincorporated Duval County) to $784.13 (Atlantic Beach).

JurisdictionBuilding permit ($50k remodel)Roofing permit ($20k re-roof)
Unincorporated Duval County$400.25$171.75
Atlantic Beach$784.13$205.00
Jacksonville$400.25$171.75
Jacksonville Beach$465.13$236.83
Neptune Beach$599.63$228.58

Estimates from each jurisdiction's sourced fee schedule, surcharges and minimum fees included. Where a schedule prices by unit, figures assume a 2,000 sq ft roof. "n/a" means the fee isn't documented in our sourced data.

New to Florida permit fees? Read our Florida permit fee guide: how schedules are set, the statutory surcharges, and what HB 803 changed in 2026.