FreeEvery fee straight from the official city and county fee schedules. No signup.

Building Permit Fees in Miami Lakes, FL (2026)

In Miami Lakes, a $20,000 re-roof runs $441.40 in permit fees, a $10,000 HVAC change-out $116.74, a $10,000 electrical panel upgrade or rewire $116.74, and a $10,000 whole-house repipe $290.93. Totals include the documented surcharges and minimum fees; where the schedule prices by unit, figures assume a 2,000 sq ft roof, a 3-ton system, 200 A service, and a 15-fixture scope. Each figure is that single permit only: a job that combines trades, like a kitchen remodel with electrical and plumbing work, pays each applicable permit. Pick a project to load it in the calculator below.

Source

Town of Miami Lakes Building Department Fee Schedule (effective 10/1/2020)

Covers building, electrical, plumbing, mechanical/HVAC, and roofing permits.

How Miami Lakes values a job: Miami Lakes prices most new construction by square footage rather than job value; valuation based fees use the estimated cost of construction, and the Town may require a copy of the executed construction contract as documentation.

Schedule effective October 1, 2020. Last verified: September 1, 2026

This schedule predates Florida's HB 803 (July 2026). Jurisdictions statewide are adopting updated schedules; we check sources weekly. What HB 803 changed

Miami Lakes Permit Fee Schedule

Every documented rule for each permit type, straight from the official schedule.

Electrical Permit Fees in Miami Lakes

Residential (1–2 family)
$11.94 per amps or fraction thereof, minimum $97.04
Commercial / 3+ units
$11.94 per amps or fraction thereof, minimum $140.20
Florida Building Code Surcharges (F.S. 553.721 and 468.631, combined)
3% of the permit fee, minimum $4.00
Miami-Dade Code Compliance Fee (Alterations, percent of value) (remodel/alteration)
0.06% of job value
Miami-Dade Code Compliance Fee (New Construction, per sq ft) (new construction)
$0.0488 per square foot (derived: $0.60 per $1,000 of value, with value set at $81.25 per sq ft for most occupancy groups per the printed Miami-Dade basis)
Technology Fee
10% of the permit fee
Change of Contractor Fee (if applicable)
$126.34
Lost Permit Card Replacement Fee (if applicable)
$35.00
Permit Extension Fee (if applicable)
$90.00
Plan Revision Fee (per trade minimum) (if applicable)
$52.16
Plan/Permit Revision Fee (Minor) (if applicable)
$111.42
Up-Front Processing Fee (credited toward permit fee)
30% of the permit fee

‡ Awaiting confirmation from the jurisdiction.

Sponsor This Page
Be the Featured Electrician in Miami Lakes

Homeowners and contractors planning a project check Miami Lakes electrical permit fees here first. One sponsor per trade, flat monthly rate.

Advertise on This Page

Miami Lakes Permit Fee Calculator

Pick a permit type and adjust the job value. Total updates instantly, itemized below.

Permit type
Project type
Kind of work
amps
60400 amps
Estimated electrical permit fee
$116.74
Electrical permit fee$23.88
200 ampss × $11.94 per amps
Minimum permit fee adjustment$73.16
Minimum permit fee: $97.04
Florida Building Code Surcharges (F.S. 553.721 and 468.631, combined)$4.00
Miami-Dade Code Compliance Fee (Alterations, percent of value)$6.00
Technology Fee$9.70
Up-Front Processing Fee (not added to total)$29.11
Paid up front; credited against the final permit fee.
Total Estimate$116.74

Assumes a $10,000.00 total job value for valuation-based surcharges.

Estimate only. Confirm with the Miami Lakes building department before applying.

Sponsor This Page
Be the Featured Electrician in Miami Lakes

Homeowners and contractors planning a project check Miami Lakes electrical permit fees here first. One sponsor per trade, flat monthly rate.

Advertise on This Page

Miami Lakes Permit Fee FAQs

How Much Is a Roofing Permit in Miami Lakes?

The roofing permit for a $20,000 residential re-roof runs $441.40, assuming a 2,000 sq ft roof where the schedule prices per unit, based on Miami Lakes's sourced fee schedule.

How Are Permit Fees Calculated in Miami Lakes?

Electrical permits are priced per amp; Plumbing permits are priced per fixture; Mechanical / HVAC permits are priced per ton; Roofing permits are priced per sq ft. New construction is priced separately from remodel and alteration work; the calculator asks which kind of job yours is. Every rate comes straight from the sourced fee schedule above. Enter your job's details for an itemized total.

What Surcharges Are Added to Permits in Miami Lakes?

On top of the base permit fee, the sourced schedule adds Florida Building Code Surcharges (F.S. 553.721 and 468.631, combined) (3% of the permit fee, minimum $4.00) and Technology Fee (10% of the permit fee). These are included in every estimate on this page.

Do I Need a Permit for a Small Residential Job in Miami Lakes?

Florida's HB 803 (effective July 2026) exempts certain single-family work under $7,500 from permitting statewide, excluding electrical, plumbing, structural, mechanical, and gas work. Confirm with the building department whether your job qualifies before skipping a permit. Read what HB 803 changed.

Where Do These Fees Come From?

Every figure on this page is sourced from Town of Miami Lakes Building Department Fee Schedule (effective 10/1/2020). See the official schedule. Last verified .

Compare Permit Fees Across Miami-Dade County

The same job, priced by each jurisdiction's own fee schedule. Across Miami-Dade County's 15 covered jurisdictions, a building permit for a $50,000 remodel runs from $239.47 (Unincorporated Miami-Dade County) to $2,250.00 (Pinecrest).

JurisdictionBuilding permit ($50k remodel)Roofing permit ($20k re-roof)
Unincorporated Miami-Dade County$239.47$322.88
Aventura$295.63$258.00
Coral Gables$1,175.00$470.00
Cutler Bayn/an/a
Hialeah$1,155.00$450.00
Homestead$1,567.50$422.00
Key Biscayne$384.75$614.25
Miami$418.75$203.50
Miami Beach$1,602.25$640.90
Miami Gardens$1,968.75$341.00
Miami Lakesn/a$441.40
Palmetto Bayn/a$333.36
Pinecrest$2,250.00$685.00
South Miami$806.25$752.50
Sweetwater$818.65$413.50

Estimates from each jurisdiction's sourced fee schedule, surcharges and minimum fees included. Where a schedule prices by unit, figures assume a 200 sq ft remodel area and a 2,000 sq ft roof. "n/a" means the fee isn't documented in our sourced data.

New to Florida permit fees? Read our Florida permit fee guide: how schedules are set, the statutory surcharges, and what HB 803 changed in 2026.