North Bay Village, FL Permit Fees (2026)
Building permit fees and building, electrical, plumbing, mechanical/HVAC, and roofing permit fees for North Bay Village, straight from the official fee schedule, with a free permit fee calculator below.
North Bay Village adopted this square-foot fee schedule on June 29, 2026 to comply with HB 803 and re-adopted it in its master fee schedule on July 28, 2026. At the June 29 meeting the Village Manager said any reimbursements due under a later revised schedule would be paid; no revision had been scheduled as of September 28, 2026. Roof permit estimates include the Village's 50% roof permit discount, which the prior fee schedule set to expire December 31, 2026 unless renewed. See the official notice
In North Bay Village, a building permit for a $50,000 remodel runs $837.50 in permit fees, a $20,000 re-roof $717.50, a $10,000 HVAC change-out $771.25, and a $10,000 electrical panel upgrade or rewire $490.00. Totals include the documented surcharges and minimum fees; where the schedule prices by unit, figures assume a 200 sq ft remodel area and a 2,000 sq ft roof. Each figure is that single permit only: a job that combines trades, like a kitchen remodel with electrical and plumbing work, pays each applicable permit. Pick a project to load it in the calculator below.
Jump to Permit Fee CalculatorNorth Bay Village Master Fee Schedule (July 28, 2026 agenda Exhibit A; Building and Permits Fees as adopted June 29, 2026)
Covers building, electrical, plumbing, mechanical/HVAC, and roofing permits. Minimum permit fee: $150.00.
How North Bay Village values a job: North Bay Village prices most permits by square foot. Where a fee is charged on the value of the work, new construction and additions use the construction values set by the Miami-Dade Board of County Commissioners, and other work uses the value you report, subject to the Building Official's approval.
Schedule effective July 28, 2026. Last verified: September 28, 2026
Schedule adopted under Florida's HB 803 permit fee rules (effective July 2026). What HB 803 changed
North Bay Village Permit Fee Schedule
Every documented rule for each permit type, straight from the official schedule.
Mechanical / HVAC Permit Fees in North Bay Village
† Corroborated across official sources, but not printed line-for-line in the linked schedule.
‡ Awaiting confirmation from the jurisdiction.
Homeowners and contractors planning a project check North Bay Village mechanical / HVAC permit fees here first. One sponsor per trade, flat monthly rate.
Advertise on This PageNorth Bay Village Permit Fee Calculator
Pick a permit type and adjust the job value. Total updates instantly, itemized below.
5 documented rates for this permit type; pick the one that matches your job.
‡ Awaiting confirmation from the jurisdiction.
North Bay Village adopted this square-foot fee schedule on June 29, 2026 to comply with HB 803 and re-adopted it in its master fee schedule on July 28, 2026. At the June 29 meeting the Village Manager said any reimbursements due under a later revised schedule would be paid; no revision had been scheduled as of September 28, 2026. Roof permit estimates include the Village's 50% roof permit discount, which the prior fee schedule set to expire December 31, 2026 unless renewed. See the official notice
This fee rate is higher than in most Florida jurisdictions; it matches North Bay Village's official schedule as published.
North Bay Village prices most permits by square foot. Where a fee is charged on the value of the work, new construction and additions use the construction values set by the Miami-Dade Board of County Commissioners, and other work uses the value you report, subject to the Building Official's approval.
Estimate only. Confirm with the North Bay Village building department before applying. Permit fees only; excludes impact fees, utility connection charges, and other non-permit charges.
Homeowners and contractors planning a project check North Bay Village mechanical / HVAC permit fees here first. One sponsor per trade, flat monthly rate.
Advertise on This PageNorth Bay Village Permit Fee FAQs
How Much Does a Building Permit Cost in North Bay Village?
How Much Does a Roofing Permit Cost in North Bay Village?
How Are Permit Fees Calculated in North Bay Village?
What Is the Minimum Permit Fee in North Bay Village?
What Surcharges Are Added to Permits in North Bay Village?
Do I Need a Permit for a Small Residential Job in North Bay Village?
Where Do These Fees Come From?
Other Jurisdictions in Miami-Dade County
Jobs inside another city's limits are permitted by that city; unincorporated areas by the county.
New to Florida permit fees? Read our Florida permit fee guide: how schedules are set, the statutory surcharges, and what HB 803 changed in 2026. Pulling a commercial permit or a small residential job? See what HB 803 lets you save.